Fagioli India was awarded the contract for Unloading, skidding and jack up operation for 3 nos. Engine Assembly at Dhamra Port, operated by ADANI GROUP, BHADRAK, ODISHA.
3 nos. Engine assembly weighted 135 Ton each were unloaded individually using FAGIOLI hydraulic EZ Gantry and Strand jack integrated system on skid track for skidding to the location. Each engine was skidded 70 meter using skid rollers, skid tracks and L15 pulling jacks to the define location.
After skidding each engine was lifted by jack up operation with the help of 8 Nos. Bottle jacks and jack down on to the foundation with precise alignment by FAGIOLI crew